Scholl Canyon Biogas Renewable Project Schedule and Emissions
Glendale
Summary
The Scholl Canyon Biogas project is facing schedule slippage, with completion expected around the end of the year. Community members raised concerns regarding air pollution, monitoring, and transparency, prompting calls for better public outreach and updated website tracking.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 2, 2026.
Impact analysis
The project budget stands at $76.4 million, with $51.8 million expended to date.
The utility and community will benefit from generating up to 11 megawatts of local renewable energy from landfill gas.
Nearby residents may experience ongoing concerns regarding air quality, emissions, and industrial activity near the landfill.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Glendale
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.